Uskmouth power stations
Series of two coal-fired power stations south-east of Newport, Wales
Series of two coal-fired power stations south-east of Newport, Wales
| Field | Value |
|---|---|
| name | Uskmouth power stations |
| image | Uskmouth power station.jpg |
| image_caption | Uskmouth B Power Station |
| Viewed from the south east, September 2007 | |
| coordinates | |
| country | Wales, United Kingdom |
| location | Newport |
| status | **A station:** Demolished |
| **B station:** Decommissioned | |
| construction_began | **A station:** 1948 |
| **B station:** 1957 | |
| commissioned | **A station:** 1952 |
| **B station:** 1959 | |
| decommissioned | **A station:** 1981 |
| **B station:** by 2024 | |
| operator | |
| th_fuel_primary | Coal |
| th_fuel_tertiary | Biomass |
| ps_chimneys | **A station:** 2 |
| **B station:** 1 | |
| ps_cooling_towers | None |
| ps_cooling_source | Sea water |
| ps_units_operational | **A station:** 4 × 60 MW |
| **B station:** 3 × 110 MW | |
| ps_electrical_capacity | **A station:** 228 MW |
| **B station:** 363 MW | |
| website |
Viewed from the south east, September 2007 B station: Decommissioned B station: 1957 B station: 1959 B station: by 2024 B station: 1 B station: 3 × 110 MW B station: 363 MW
The Uskmouth power stations (also known as the Fifoots Point power stations) refers to a series of two coal-fired power stations at the mouth of the River Usk in the south-east of Newport, Wales.
The first of the two stations, Uskmouth A power station, was built in the 1940s and demolished in 2002. The second station, Uskmouth B power station, was built in the 1950s and as of 2023 has been decommissioned and mothballed.
Uskmouth A
Uskmouth A power station was authorised in 1947, and building started in April 1948. The first generating set was commissioned in December 1952, followed by other sets in September 1953, March 1954, September 1954, June 1956 and finally December 1956 for a set scrapped in January 1956. It comprised four Fraser and Chalmers / GEC 60 MW hydrogen cooled 11.8 kV turbo-alternators, these were supplied with steam at 62.1 bar and 482 °C. The 12 Babcock and Wilcox pulverised fuel boilers were capable of delivering 320.0 kg/s of steam.
The generating capacity and output of the station was as follows.
| Year | Capacity MW | Electricity supplied GWh |
|---|---|---|
| 1954 | 168 | 618.239 |
| 1955 | 228 | 1276.305 |
| 1956 | 228 | 1409.361 |
| 1957 | 342 | 1575.815 |
| 1958 | 342 | 2149.267 |
| 1961 | 360 | 1489.1 |
| 1962 | 360 | 1241.6 |
| 1963 | 360 | 1257.1 |
| 1967 | 360 | 1138.711 |
| 1971 | 360 | 887.514 |
| 1979 | 240 | 148.250 |
| 1981 | 228 | 19.802 |
On 18 January 1956, the No. 5 60-MW generator, a conventional steam turbine with a low pressure rotor driving a hydrogen cooled generator, suffered a catastrophic overspeed event. In the resulting explosion, two workers were killed and nine injured, and the turbine and generator were completely destroyed. Wreckage from the blast was propelled through the walls of the building and thrown as far as several hundred yards. Remarkably, the remaining four generator sets, which operating under full loads, experienced no interruption in operation.
The A station was closed on 26 October 1981 with a generating capacity of 228 megawatts. The station was demolished in 2002.
Uskmouth B
Uskmouth B power station (or Uskmouth Power as it is now known) was authorised in May 1957 and built in 1959. It had a generating capacity of 363 MW, which is enough to power 360,000 homes, or the surrounding area of Newport. The pulverised fuel boilers were capable of delivering 324.0 kg/s of steam at 103.4 bar and 538 °C. It was situated in an essential position for the National Grid, as there are very few power stations situated in the south of Wales. The annual electricity output of Uskmouth B was:
| Year | Electricity supplied, GWh |
|---|---|
| 1960–1 | 1961–2 |
| 9.766 | 1006.7 |
It was officially opened on Friday June 14 1963 by David Lewis, 1st Baron Brecon, it had cost £19.5m.
Initially operated by the Central Electricity Generating Board, the station's operations were handed over to National Power with privatisation in 1990. The station was then closed in 1995. But in 1998, it was purchased by AES. The station was given a £120 million refurbishment to bring it up to date with legislative requirements. New environmental equipment was installed and it was given a refurbishment which is thought to have extended the station's life by 25 years. The station's generating capacity was also increased to 393 MW. In 2001 the work was completed and the station was reopened. However, only a year later the plant passed into receivership, but had a brief period of operating in the winter between 2003 and 2004. In June 2004 the station was put back into full operation, when it was bought by Welsh Power, who were then known as Carron Energy. Welsh Power sold it to SSE (Scottish and Southern Energy plc) in 2009 for £27m. In April 2013 one of the three remaining blocks was closed, leaving the power station with a remaining generation capacity of 260 MW.
The station was one of the cleanest coal-fired power stations in the United Kingdom,{{cite web
The station employed 90 people.
The station was earmarked for closure in 2014 and subsequently mothballed. However, in 2015, plans were announced to instead convert the station to run fully on pellets of biomass and waste plastic, as part of a scheme to regenerate the area and create hundreds of jobs. These plans then took priority and as a result, Uskmouth saw very infrequent use as a coal plant; with April 2017 being the last occasion.
In 2017, Simec Atlantis Energy joined a partnership to undertake this transformation by 2020. In 2019, it was reported that the plant would be running on 50% pellets of plastic and 50% pellets of cardboard and paper by 2021 and was expected to operate for 20 years. However, in April 2022, Simec Atlantis Energy announced it was abandoning the waste-to-energy conversion project, following opposition from environmental groups and the call in of the conversion application by the Welsh Government.
In December 2023, the site's operator Simec Uskmouth Power Ltd obtained planning consent to demolish the station's two banks of cooling towers, with the demolition expected to be completed by May 2024.
In January 2024, Simec was granted planning permission to construct a battery energy storage system on the site of the to-be-demolished cooling towers. Media reporting of this development also confirmed that Uskmouth B power station was decommissioned as of that date. In 2025, size was estimated at 250 MW for 5 hours.
Severn Power Station
An 832MW combined cycle power plant running on natural gas, known as Severn Power Station, was built on the site of Uskmouth A by Siemens. It comprises two gas turbines and two steam turbines, each operating on a single shaft, and entered commercial operations in November 2010. It was initially reported that it would cost £400 million to build and create 650 construction jobs.
Originally owned and operated by the Danish company DONG Energy (now Ørsted), the station was acquired in December 2013 by MPF Holdings, which later changed its name to Calon Energy. The station was put into a 'dormant state' in August 2020 following Calon Energy entering administration.
Uses in culture
In 2006, the station was used as a location for two episodes of Doctor Who. In the episodes "Rise of the Cybermen" and "The Age of Steel", the station was used as the setting for the Cybermen Factory. It was then used again for the 2011 Christmas special "The Doctor, the Widow and the Wardrobe" as spaceship corridors, filmed on 20 September 2011. In 2014, the station was once again used for two episodes "Into the Dalek" and "Time Heist".
References
References
- "The history of power generation at Uskmouth". Welsh Power.
- (1959). "Garcke's Manual of Electricity Supply vol. 56". Electrical Press.
- ''CEGB Statistical Yearbook'', 1981, CEGB, London.
- CEGB. (1972). "CEGB Statistical Yearbook 1972". CEGB.
- CEGB, ''Annual report and accounts'', 1961, 1962 & 1963
- (1958). "Failure of a 60-MW Steam Turbo-Generator at Uskmouth Power Station". Proceedings of the Institution of Mechanical Engineers.
- Mr. Redmond. (16 January 1984). "Coal-fired Power Stations". [[Hansard.
- Blake, Aled. (19 July 2005). "£400m power station may create 645 jobs". [[Wales Online]].
- (25 April 2006). "SALE OF POWER STATION BY THE RUTLAND FUND". Lexicon Partners.
- CEGB. (1966). "CEGB Statistical Yearbooks 1964, 1965, 1966, 1972, 1982". CEGB.
- ''Times'' Saturday June 15 1963, page 6
- (2003). "Generation disconnections since 1991". [[National Grid (Great Britain).
- (18 October 2000). "Rotork actuators in power station refurbishment". Engineering Talk.
- (January 2026). "Acquisition of Uskmouth power station". [[Scottish and Southern Energy]]}}{{Dead link.
- "Uskmouth power station closure". [[Scottish and Southern Energy]].
- (8 December 2007). "Steelmaker's efforts to improve environmental impact sees CO2 levels halved since the 1970s". Wales Online.
- "Clean Coal Technology". UK Parliament Publications and Records.
- "Welcome to Uskmouth Power". Welsh Power.
- (9 May 2014). "Coal-fired power station at Uskmouth to shut". [[BBC News]].
- Barry, Sion. (25 June 2015). "Uskmouth Power Station reopens in a move securing 40 jobs as owners confirm ambitious energy hub plans". [[Media Wales]].
- Evans, Simon. (10 February 2016). "Countdown to 2025: Tracking the UK coal phase out". [[Carbon Brief]].
- Rose, Alice. (3 February 2018). "Uskmouth Power Station conversion will lead to hundreds of new jobs". [[South Wales Argus]].
- (5 November 2018). "SIMEC Atlantis Energy surges following Uskmouth power project update". Proactive Investors.
- (2019-11-07). "Power move: the coal-fired plant to be fuelled by plastic waste".
- (28 April 2022). "Uskmouth conversion to burn waste abandoned; battery planned for site".
- "Uskmouth Conversion Project". Simec Atlantis Energy.
- (23 February 2021). "Climate activists claim Uskmouth power station plan will emit 1,550,000 tonnes of carbon every year". Trinity Mirror North West & North Wales.
- (9 February 2021). "Why Newport Council has been 'barred' from Uskmouth Power Station decision". Trinity Mirror North West & North Wales.
- (18 December 2023). "Demolition of cooling towers at Uskmouth Power Station can go ahead". [[South Wales Argus]].
- Thomas, Nicholas. (13 January 2024). "Battery plant to open on site of Uskmouth B Power Station". [[South Wales Argus]].
- (19 May 2025). "SAE and Econergy partner on five-hour battery storage project in the UK".
- (21 August 2007). "£400m power station bid approved". [[BBC News]].
- "Welcome to Severn Power Station".
- (24 August 2020). "Calon Energy's administrators put two power plants in 'dormant state'". BBC News.
- "Uskmouth Power Station". Chuck Foster, News In Time Space Ltd.
- "The Doctor, the Widow and the Wardrobe - The Fourth Dimension". BBC.
- "Into the Dalek: Fact File". [[BBC One]].
- "Time Heist: The Fact File". [[BBC One]].
This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.
Ask Mako anything about Uskmouth power stations — get instant answers, deeper analysis, and related topics.
Research with MakoFree with your Surf account
Create a free account to save articles, ask Mako questions, and organize your research.
Sign up freeThis content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.
Report