Nuclear power in China

none


none

According to the National Nuclear Safety Administration of China, as of 5 Jan, 2026, there are 59 nuclear power-plants operating in mainland China, second only to the United States which has 94. The installed power sits at 62.219 GW, ranked third after US's 96.95 GW and France's 63.02 GW,Archived stats from IAEA PRIS:

YearUSAFranceChina
2018 [https://web.archive.org/web/20181231075836/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx](https://web.archive.org/web/20181231075836/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx)996343
2019 [https://web.archive.org/web/20191219033947/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx](https://web.archive.org/web/20191219033947/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx)986346
2020 [https://web.archive.org/web/20201108103337/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx](https://web.archive.org/web/20201108103337/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx)976147
2021 [https://web.archive.org/web/20211225140501/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx](https://web.archive.org/web/20211225140501/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx)966150
2022 [https://web.archive.org/web/20221126222131/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx](https://web.archive.org/web/20221126222131/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx)956152
2023 [https://web.archive.org/web/20231226233627/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx](https://web.archive.org/web/20231226233627/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx)966153
2024 [https://web.archive.org/web/20241222155326/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx](https://web.archive.org/web/20241222155326/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx)976154
2025 [https://web.archive.org/web/20251227180702/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx](https://web.archive.org/web/20251227180702/https://pris.iaea.org/PRIS/WorldStatistics/OperationalReactorsByCountry.aspx)976356

According to the National Bureau of Statistics, in 2026, nuclear power in China had a total installed power of 62.219 GW comprising 2.1% of the nation's total. They produced 450.85 TWh of electricity (ranked second globallyArchived stats from IAEA PRIS:

YearUSAFranceChina
2017805 [https://web.archive.org/web/20181221230359/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US](https://web.archive.org/web/20181221230359/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US)379 [https://web.archive.org/web/20181230233256/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR](https://web.archive.org/web/20181230233256/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR)247 [https://web.archive.org/web/20181225074950/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN](https://web.archive.org/web/20181225074950/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN)
2018807 [https://web.archive.org/web/20190707165149/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US](https://web.archive.org/web/20190707165149/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US)393 [https://web.archive.org/web/20191117112915/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR](https://web.archive.org/web/20191117112915/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR)287 [https://web.archive.org/web/20190719135741/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN](https://web.archive.org/web/20190719135741/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN)
2019809 [https://web.archive.org/web/20201103113552/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US](https://web.archive.org/web/20201103113552/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US)382 [https://web.archive.org/web/20201125050235/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR](https://web.archive.org/web/20201125050235/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR)330 [https://web.archive.org/web/20201125044530/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN](https://web.archive.org/web/20201125044530/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN)
2020790 [https://web.archive.org/web/20211225071726/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US](https://web.archive.org/web/20211225071726/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US)380 [https://web.archive.org/web/20211225071736/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR](https://web.archive.org/web/20211225071736/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR)366 [https://web.archive.org/web/20211220073338/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN](https://web.archive.org/web/20211220073338/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN)
2021787 [https://web.archive.org/web/20221126222358/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US](https://web.archive.org/web/20221126222358/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US)361 [https://web.archive.org/web/20221201025335/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR](https://web.archive.org/web/20221201025335/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR)407 [https://web.archive.org/web/20221126222131/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN](https://web.archive.org/web/20221126222131/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN)
2022772 [https://web.archive.org/web/20231227075000/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US](https://web.archive.org/web/20231227075000/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US)279 [https://web.archive.org/web/20231226180616/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR](https://web.archive.org/web/20231226180616/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR)418 [https://web.archive.org/web/20231209021317/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN](https://web.archive.org/web/20231209021317/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN)
2023775 [https://web.archive.org/web/20241225132851/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US](https://web.archive.org/web/20241225132851/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US)320 [https://web.archive.org/web/20241221141605/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR](https://web.archive.org/web/20241221141605/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR)433 [https://web.archive.org/web/20241227185825/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN](https://web.archive.org/web/20241227185825/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN)
2024782 [https://web.archive.org/web/20251205034048/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US](https://web.archive.org/web/20251205034048/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=US)362 [https://web.archive.org/web/20251230124142/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR](https://web.archive.org/web/20251230124142/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=FR)451 [https://web.archive.org/web/20251231112255/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN](https://web.archive.org/web/20251231112255/https://pris.iaea.org/PRIS/CountryStatistics/CountryDetails.aspx?current=CN)

Nuclear power has been looked into as an alternative to coal due to increasing concerns about air quality, climate change and fossil fuel shortages. The China General Nuclear Power Group has articulated the goal of 200 GW by 2035, produced by 150 additional reactors.

China has two major nuclear power companies, the China National Nuclear Corporation operating mainly in northeast China, and the China General Nuclear Power Group (formerly known as China Guangdong Nuclear Power Group) operating mainly in south-east China.

China aims to maximize self-reliance on nuclear reactor technology manufacturing and design, although international cooperation and technology transfer are also encouraged. Advanced pressurized water reactors such as the Hualong One are the mainstream technology in the near future, and the Hualong One is also planned to be exported. China plans to build as many as thirty nuclear power reactors in countries involved in the Belt and Road Initiative by 2030. By mid-century, fast neutron reactors are seen as the main technology, with a planned 1400 GW capacity by 2100. China is also involved in the development of nuclear fusion reactors through its participation in the ITER project, having constructed an experimental nuclear fusion reactor known as EAST located in Hefei, as well as research and development into the thorium fuel cycle as a potential alternative means of nuclear fission.

History

1950–1958

In the Cold War, Beijing's initial motivation for developing nuclear power was largely driven by security concerns. Between 1950 and 1958, Chinese nuclear power construction heavily relied on cooperation with the USSR. The first initiative was launched with the establishment of the China-Soviet Union Nonferrous Metals and Rare Metals Corporation and the first central atomic research facility, the Institute of Atomic Energy of the Chinese Academy of Sciences in Beijing. In February 1955, a chemical separation plant for the production of weapons-grade U-235 and plutonium was created with Soviet aid in Xinjiang and in April the Changchun Institute of Atomic Energy was established. Several months later, on 29 April 1955, the Sino-Soviet Atomic Cooperation Treaty was signed. The China National Nuclear Corporation (CNNC) was also established in 1955. In addition to cooperation with the USSR, China began to learn nuclear technology by sending students to the USSR. In December 1958, nuclear power development had become the top priority project in the Draft Twelve Year Plan for Development of Science and Technology.

1959–1963

The second phase was characterized by the goal of being completely self-sufficient in nuclear power development. In June 1959, the USSR officially ended any forms of nuclear aid to China, withdrawing Soviet technicians. China suffered but continued nuclear power development through massive research and input. In order to rapidly strengthen its atomic energy industry, the Central Committee decided that China must dedicate further resources exclusively to nuclear-related activities. Consequently, the Institute of Atomic Energy created branch institutes of research organizations in every province, major city, and autonomous region. By the end of 1963, China had built more than forty chemical separation plants for the extraction of uranium and thorium. In the year between 1961 and 1962, China accomplished significant achievements in nuclear development which consolidated future applications. From 1959 to 1963, a gaseous diffusion plant utilizing a large 300 MW reactor was under construction at Lanzhou. It was estimated that the Chinese invested over $1.5 billion in the construction of this plant.

1964 – 2012

After the explosive progress in the 1950s, Chinese nuclear development slowed down, possibly because of the Cultural Revolution, so only one nuclear test took place in 1970. On 8 February 1970, China issued its first nuclear power plan, and the 728 Institute (now known as Shanghai Nuclear Engineering Research and Design Institute) was established.

Qinshan Nuclear Power Plant, constructed in 1984, was the first independently designed and built nuclear power plant. It was successfully connected to the grid on 15 December 1991. The reactor is of type CNP-300.

After the 1986 Chernobyl disaster, Beijing emphasized that it would not change its nuclear development policy, but would still explore a national emergency management strategy.

One year after Chernobyl, China began construction on the Daya Bay nuclear plant, located between Shenzhen and Hong Kong. Over 72% of Hong Kong residents surveyed opposed the plant, and more than one million residents signed a petition against the project. Despite this public protest, Beijing pushed forward with construction, with then-Minister of Nuclear Industry Jiang Xinxiong saying, "The government has not changed and will not change its decision to build a nuclear plant at Daya Bay," at a press conference in 1986.

In 1991, China created the National Nuclear Accident Emergency Committee to plan and coordinate nationwide nuclear accident emergency preparations and rescue operations.

Along with Chinese economic reform, China continued to demand expansion of its electricity sector. As part of China's tenth Five-Year Plan (2001–2005), a key component of energy policy was to "guarantee energy security, optimize energy mix, improve energy efficiency, protect the ecological environment.” By 2002, China had two operational nuclear power plants.

In 2007, the Hu Jintao administration set the goal of doubling the amount of nuclear energy in China's total installed capacity, which resulted in the major growth of business opportunities in China's nuclear power sector.

Immediately after the 2011 Fukushima nuclear accident, Beijing froze all reactor approvals pending a safety review. By late 2012, the Chinese State Council approved the Nuclear Power Safety Plan and the Mid- and Long-Term Nuclear Development Plan, resuming reactor deployment as long as new projects met stricter Generation III safety standards.

In 2012, Hu emphasized "the irreplaceable role of nuclear energy in ensuring energy security and climate change".

2013 – present

The nuclear safety plan of 2013 stated that beyond 2016, only Generation III plants would be started, and until then only a very few Generation II+ plants would be started.

In 2014, China still planned to have 58 GW of capacity by 2020. However, due to reevaluation following the Fukushima Daiichi nuclear disaster in Japan, few plants commenced construction after 2015, and this target was not met.

In 2019, China had a new target of 200 GWe of nuclear generating capacity by 2035, which is 7.7% of the predicted total electricity generating capacity of 2600 GWe. By the end of December 2020, the total number of nuclear power units in operation on the Chinese mainland reached 49, with a total installed capacity of 51 GWe, ranking third in the world in terms of installed capacity and second in the world in terms of power generation in 2020; with 16 nuclear power units under construction, the number of units under construction and installed capacity have ranked first in the world for many years. By 2035, nuclear power is planned to account for 10% of electricity generation.

As of 2020, China had 41 additional nuclear reactors planned and 168 proposed reactors under consideration. China's under-construction reactors accounted for 27% of worldwide reactors under construction. As of at least 2023, China's goals for nuclear power expansion are the most ambitious of any country.

In 2021, China's Environmental Protection and Resources Conservation Committee announced an action plan which emphasized the deployment and development of next-generation nuclear power technology to reduce carbon dioxide emissions.

In 2024, the Information Technology and Innovation Foundation think tank stated that globally, China leads or matches in commercial nuclear power technology, and is likely 10 to 15 years ahead in Generation IV reactor technology.

Between 2015 and 2024, China built 37 reactors with an average time from first concrete to grid connection of 6.3 years (beating the global average of 9.4 years). China also recorded the fastest build time in that period at just 4.1 years.

As of 2025, China is the world's largest investor in nuclear energy, with 29 reactors currently under construction. This represents nearly half of all nuclear reactors being built globally. China is projected to surpass the United States as the world's leading producer of nuclear energy in the coming years. This expansion is consistent with the country's stated climate strategy. In terms of total prospective capacity, China leads with nearly 125 GWe in announced and under-construction projects, almost four times that of second-place Russia.

Safety and regulation

The National Nuclear Safety Administration (NNSA), under the China Atomic Energy Authority (CAEA), is the licensing and regulatory body which also maintains international agreements regarding safety. It was set up in 1984 and reports to the State Council directly. In relation to the AP1000, NNSA works closely with the US Nuclear Regulatory Commission. China has been a member of the International Atomic Energy Agency (IAEA) since 1984.

China has requested and hosted 12 Operational Safety Review Team (OSART) missions from IAEA teams as of October 2011, and each plant generally has one external safety review each year, either OSART, WANO peer review, or CNEA peer review (with the Research Institute for Nuclear Power Operations).

Following the Fukushima Daiichi nuclear disaster in Japan, China announced on 16 March 2011, that all nuclear plant approvals were being frozen, and that "full safety checks" of existing reactors would be conducted. Although Zhang Lijun, Vice Minister of Environmental Protection, has indicated that China's overall nuclear energy strategy would continue,

China's current methods for storing spent nuclear fuel (SNF) are only sustainable until the mid-2020s, and a policy to handle SNF needs to be developed.

In 2007, China's National Nuclear Safety Administration authorized three state-owned enterprises to own and operate nuclear power plants: the China National Nuclear Corporation, the China General Nuclear Power Group, and State Power Investment Corporation.

In 2017, new laws strengthened the powers of the National Nuclear Safety Administration, creating new "institutional mechanisms", a clearer "division of labour" and more disclosure of information.

IAEA Director General Rafael Grossi made his first official visit in May 2023, signing several agreements with China's nuclear regulator, the China Atomic Energy Authority. Grossi said "China is one of the IAEA’s most important partners and a global leader in nuclear energy".

Reactor technologies

Imported technology

CANDU reactors

In 1998 construction of two AECL 728 MW CANDU-6 reactors at Qinshan Nuclear Power Plant started. The first went online in 2002, the second in 2003. CANDU reactors can use low-grade reprocessed uranium from conventional reactors as fuel, thereby reducing China's stockpile of spent nuclear fuel.

VVER

Russia's Atomstroyexport was the general contractor and equipment provider for the Tianwan AES-91 power plants using the V-428 version of the well-proven VVER-1000 reactor with a 1060 MWe capacity. Construction started in 1999. Two further Tianwan units started in 2012, using the same version of the VVER-1000 reactor.

On 7 March 2019, China National Nuclear Corporation (CNNC) and Atomstroyexport signed the detailed contract for the construction of four VVER-1200s, two each at the Tianwan Nuclear Power Plant and the Xudabao Nuclear Power Plant. Construction was scheduled to begin in May 2021, and commercial operation of all the units is expected between 2026 and 2028.

EPR

In 2007, negotiations began with the French company Areva concerning the EPR third-generation reactors. Two Areva 1660 MWe EPR reactors were built at Taishan, with construction starting in 2009.

AP1000

The Westinghouse AP1000 was planned to be the main basis of China's move to Generation III technology. In July 2018, the first of four AP1000 reactors was connected to the grid.

Following Westinghouse's bankruptcy in 2017, it was decided in 2019 to build the Hualong One rather than the AP1000 at Zhangzhou.

Chinese developments

CNP / ACP series

Main article: CNP / ACP nuclear reactors

The CNP Generation II nuclear reactors (and Generation III successor ACP) were a series of nuclear reactors developed by China National Nuclear Corporation (CNNC), and are predecessors of the more current Hualong One design.

The CNP series of Generation II reactors started with the CNP-300 pressurized water reactor, which was the first reactor design developed domestically in China. The first unit began operation at Qinshan Nuclear Power Plant in 1991.

A larger version of the reactor, the CNP-600 was developed based on both the CNP-300 and the M310 reactor design used in Daya Bay Nuclear Power Plant. It was installed at Changjiang Nuclear Power Plant, with two units operational from 2015 and 2016, respectively. A Generation III ACP-600 successor was also developed, but none were built.

A three-loop, 1000-MW version of the CNP reactor, the CNP-1000, was under development since the 1990s with the help of vendors Westinghouse and Framatome (now AREVA). 4 units of the CNP-1000 were later built at Fuqing NPP. Further work on the CNP-1000 was stopped in favour of the ACP-1000.

In 2013, China announced that it had independently developed the Generation III ACP-1000, with Chinese authorities claiming full intellectual property rights over the design. As a result of the success of the Hualong One project, no ACP-1000 reactors have been built to date. CNNC had originally planned to use the ACP-1000 in Fuqing reactors 5 and 6 but switched over to the Hualong One.

CPR-1000 / ACPR-1000

Main article: CPR-1000

The CPR-1000 was a Generation II reactor developed by China General Nuclear Power Group (CGN). It is the most numerous reactor type in China, with 22 units operational. This reactor type is a Chinese development of the French 900 MWe three cooling loop design imported in the 1990s, with most of the components now built in China. Intellectual property rights are retained by Areva, which affects CPR-1000 overseas sales potential.

China's first CPR-1000 nuclear power plant, Ling Ao-3, was connected to the grid on 15 July 2010. The design has been progressively built with increasing levels of Chinese components. Shu Guogang, GM of China Guangdong Nuclear Power Project, said, "We built 55 percent of Ling Ao Phase 2, 70 percent of Hongyanhe, 80 percent of Ningde and 90 percent of Yangjiang Station."

In 2010, the China Guangdong Nuclear Power Corporation announced the ACPR1000 design, a further design evolution of the CPR-1000 to a Generation III level, which would also replace components subject to intellectual-property restrictions. CGNPC aimed to be able to independently market the ACPR1000 for export by 2013. A number of ACPR1000 are under construction in China, but for export, this design was superseded by the Hualong One.

Hualong One

Main article: Hualong One

bibcode=2016Engin...2...79X }}</ref><br />Red line − active systems<br />Green line − passive systems<br />IRWST − in-containment refuelling water storage tank

Hualong One is jointly developed by the China National Nuclear Corporation (CNNC) and China General Nuclear Power Group (CGN), based on the three-loop ACP1000 of CNNC and ACPR1000 of CGN, which in turn are based on the French M310.

Since 2011, CNNC has been progressively merging its ACP-1000 nuclear power station design with the CGN ACPR-1000 design, while allowing some differences, under the direction of the Chinese nuclear regulator. Both are three-loop designs originally based on the same French M310 design used in Daya Bay with 157 fuel assemblies, but went through different development processes (CNNC's ACP-1000 has a more domestic design with 177 fuel assemblies, while CGN's ACPR-1000 is a closer copy with 157 fuel assemblies). In early 2014, it was announced that the merged design was transitioning from preliminary design to detailed design. Power output will be 1150 MWe, with a 60-year design life, and will use a combination of passive and active safety systems with a double containment. CNNC's 177 fuel assembly design was retained.

After the merger, both companies retain their own supply chain and their versions of the Hualong One will differ slightly (units built by CGN will retain some features from the ACPR1000) but the design is considered to be standardised. Some 85% of its components will be made domestically.

The Hualong One power output will be 1170 MWe gross, 1090 MWe net, with a 60-year design life, and would use a combination of passive and active safety systems with a double containment.

The Hualong One is now largely seen as the replacement for all previous Chinese nuclear reactor designs, and has been exported overseas.

Hualong Two

CNNC plans to start building a follow-on version, named Hualong Two, by 2024. It will be a more economical version using similar technology, reducing build time from 5 years to 4, and reducing costs by around a fourth from 17,000 yuan per kW to 13,000 yuan per kW.

CAP1400 (Guohe One)

Main article: CAP1400

In September 2020, China's State Power Investment Corporation launched a design based on the Westinghouse AP1000 for more widespread deployment consideration. It was given the name Guohe One.

, the construction of six CAP1000 was approved by the State Council: Haiyang 3 & 4, Lianjiang 1 & 2, and Sanmen 3 & 4. Construction of Sanmen 3 officially started in June 2022, and of Haiyang 3 in July 2022.

Generation IV reactors

China is developing several generation IV reactor designs.

In December 2023, China’s HTR-PM, a high-temperature gas-cooled reactor at Shidao Bay, entered commercial operation. HTR-PM is a small modular reactor which connects two helium-cooled reactor modules to a single steam turbine, outputting energy and super-heated steam. These reactors are inherently safe as they demonstrate “walk-away” behavior. Emergency tests conducted in proved the reactors could cool down naturally without human intervention or backup core-cooling systems. This was the first successful demonstration of this inherent-safety behavior in a commercial reactor. In 2024, the state energy firm Huaneng connected HTR-PM to a local steam heating network, replacing ~3,700 tonnes of coal per heating season.

The HTR-PM is a descendant of the AVR reactor, and it is partly based on the earlier Chinese HTR-10 reactor. A sodium-cooled fast reactor, the CFR-600, is also under construction.

ACP100 small modular reactor

In July 2019, China National Nuclear Corporation announced it would start building a demonstration ACP100 small modular reactor (SMR) on the north-west side of the existing Changjiang Nuclear Power Plant by the end of the year. Design of the ACP100 started in 2010 and it was the first SMR project to pass an independent safety assessment by International Atomic Energy Agency in 2016. It is also referred to as Linglong One and is a fully integrated reactor module with an internal coolant system, with a 2-year refuelling interval, producing 385 MWt and about 125 MWe, and incorporates passive safety features, and can be installed underground.

Nuclear power plants

Most nuclear power plants in China are located on the coast and generally use seawater for cooling in a direct once-through cycle. In 2009, The New York Times reported that China was placing many of its nuclear plants near large cities, and there was a concern that tens of millions of people could be exposed to radiation in the event of an accident. China's neighboring Daya Bay and Lingao nuclear plants have around 28 million people within a 75-kilometre radius that covers Hong Kong.

Future projects

Following the Fukushima accident and consequent pause in approvals for new plants, the target adopted by the State Council in October 2012 became 60 GWe by 2020, with 30 GWe under construction. In 2015, the target for nuclear capacity on line in 2030 was 150 GWe, providing almost 10% of electricity, and 240 GWe in 2050 providing 15%.

However, from 2016 to 2018, there was a further hiatus in the new build programme, with no new approvals for at least two years, causing the programme to slow sharply. Delays in the Chinese builds of AP1000 and EPR reactors, together with the bankruptcy in the U.S. of Westinghouse, the designer of the AP1000, have created uncertainties about the future direction. Also, some regions of China now have excess generation capacity, and it has become less certain to what extent electricity prices can economically sustain nuclear new build while the Chinese government is gradually liberalising the generation sector.

In 2018, a Nuclear Engineering International journal analysis suggests a below-plan capacity of 90 GWe is plausible for 2030. , China had 68 GW of operational nuclear power, with 34 GW under construction, and 147 proposed. (see Table below)

Bloomberg News reported that the 2020 National People's Congress supported future building of 6 to 8 reactors a year, which Bloomberg considered likely to be dominated by the domestic Hualong One design. In 2019, China had a new target of 200 GWe of nuclear generating capacity by 2035, which is 7.7% out of predicted total electricity generating capacity of 2600 GWe.

The role of the IPPs

The first major successful profitable commercial project was the Daya Bay Nuclear Plant, which is 25% owned by CLP Group of Hong Kong and exports 70% of its electricity to Hong Kong. Such imports supply 20% of Hong Kong's electricity.

In order to access the capital needed to meet the 2020 target of 80GW, China has begun to grant equity in nuclear projects to China's Big Five power corporations:

  • Huaneng Group,
  • Huadian Group – Fujian Fuqing nuclear power project II and III
  • Datang Group,
  • China Power Investment Group – Jiangxi Pengze Nuclear
  • Guodian Group Like the two nuclear companies China National Nuclear Corporation and China Guangdong Nuclear Power Group (CGNPG) the Big Five are State-owned "Central Enterprises" (中央企业) administered by SASAC. However, unlike the two nuclear companies, they have listed subsidiaries in Hong Kong and a broad portfolio of thermal, hydro and wind.

Summary of nuclear power plants

PLEASE UPDATE THE TOTALS WHEN CHANGING THE TABLE

--

Nuclear power plantoperational reactorsreactors under constructionreactors plannedtotalunitsnet capacity
(MW)unitsnet capacity
(MW)unitsnet capacity
(MW)unitsnet capacity
(MW)Total
Bailongcolspan=211,10057,10068,200
Changjiang21,20232,400colspan=253,602
Daya Bay (Dayawan)21,888colspan=2colspan=221,888
Fangchenggang44,000colspan=222,20066,200
Fangjiashan22,024colspan=2colspan=222,024
Fuqing66,000colspan=2colspan=266,000
Haiyang22,30022,20022,20066,700
Hongyanhe66,366colspan=2colspan=266,366
Lianjiangcolspan=222,44844,64067,088
Ling Ao43,914colspan=2colspan=243,914
Lufeng (Shanwei)colspan=222,20044,40066,600
Ningde44,07211,01811,01866,108
Pengzecolspan=2colspan=222,20022,200
Qinshan74,110colspan=2colspan=274,110
San'aocolspan=222,20044,40066,600
Sanmen22,31422,32622,00066,640
Shidao Bay (Shidaowan)2160033668colspan=255268
Taishan23,320colspan=2colspan=223,320
Taipinglingcolspan=2333481111644464
Tianwan66,08022,200colspan=288,280
Wuwei12110colspan=2212
Xianningcolspan=2colspan=222,20022,200
Xiapucolspan=221,000colspan=221,000
Xudabaocolspan=244,400colspan=244,400
Yangjiang66,120colspan=2colspan=266,120
Zhangzhou22,42422,42422,20066,600
**59****62,219****28****29,808****27****31,474****116****120,846**

Where multiple reactors are operational/under construction/planned at a given site, the capacity given is to be understood for all reactors at this site applicable to the given column, not a per reactor figure.

Fuel cycle

China is evaluating the construction of a high level waste (HLW) repository in the Gobi Desert, probably constructed near Beishan starting around 2041.

Starting in about the 2010s, China has been making serious efforts towards nuclear reprocessing. While those plants are ostensibly civilian in nature, there is concern as to the Dual Use applicability of the technology with media articles headlined "China nuclear reprocessing to create stockpiles of weapons-level materials: Experts" China has also pioneered the use of a reprocessed uranium / depleted uranium mixture "natural uranium equivalent" in its Pressurized Heavy Water Reactors at Qinshan Nuclear Power Plant. Unlike the similar "DUPIC" process ("direct use of spent PWR fuel in CANDU") pioneered in South Korea, this process separately recovers the reactor grade plutonium for other uses, fueling the heavy water reactor with the uranium content of the spent fuel alone.

Companies

China's domestic market for uranium is highly concentrated because Chinese policy identifies uranium as a strategic resource and only select companies are authorized to mine it. The country's civilian nuclear industry and its mining industry are largely concentrated in China General Nuclear Power Group and China National Nuclear Corporation, two state-owned enterprise that report to the State Council.

China National Nuclear Corporation was founded in 1988 as a state-owned enterprise supervised by the State-owned Assets Supervision and Administration Commission (SASAC), and was constituted from the former Ministry of Nuclear Industry. It is the only exporter of Chinese nuclear power plants.

China General Nuclear Power Group was founded in 1994 as the China Guangdong Nuclear Power Group and changed to its current name in 2013. It is also supervised by SASAC. Its headquarters are in Shenzhen. As of 2017, China General Nuclear Power Group manages 20 reactors.

  • State Nuclear Power Technology Corporation
  • China Nuclear International Uranium Corporation

Research

[[Daya Bay Reactor Neutrino Experiment

In January 2011, the Chinese Academy of Sciences began the TMSR research and development project to create reactors which, among other advances, will be air-cooled. A small prototype reactor of this type, the TMSR-LF1, was planned to be sited in Gansu province, in an industrial park in Minqin County. A ten-year operating license was issued in June 2023. Criticality was first achieved in October of that same year. In June 2024, full power (2MWt) operation was achieved, and in October, it operated at full power for 10 days with thorium in the molten salt; Protactinium-233 was detected, indicating successful nuclear breeding.

In February 2019, China's State Power Investment Corporation (SPIC) signed a cooperation agreement with the Baishan municipal government in Jilin province for the Baishan Nuclear Energy Heating Demonstration Project, which would use a China National Nuclear Corporation DHR-400 (District Heating Reactor 400 MWt).

Public opposition

China experienced civil protests over its ambitious plans to build more nuclear power plants following the Fukushima nuclear disaster. There has been an "inter-provincial squabble" over a nuclear power plant being built near the southern bank of the Yangtze River. The plant in the centre of the controversy is located in Pengze county in Jiangxi, and across the river the government of Wangjiang county in Anhui wants the project shelved.

More than 1,000 people protested in Jiangmen City Hall in July 2013 to demand that authorities abandon a planned uranium-processing facility that was designed as a major supplier to nuclear power stations. The Heshan Nuclear Power Industry Park was to be equipped with facilities for uranium conversion and enrichment as well as the manufacturing of fuel pellets, rods and finished assemblies. Protesters feared the plant would adversely affect their health, and the health of future generations. As the weekend protest continued, Chinese officials announced the state-run project's cancellation.

By 2014, concerns about public opposition caused Chinese regulators to develop public and media support programmes, and developers to begin outreach programmes including site tours and visitor centres.

In 2020, Bloomberg News reported that public opposition had stopped nuclear power construction on inland river sites, and caused the cancellation of a nuclear fuel plant in Guangdong in 2013.

References

References

  1. "全国年度统计公报".
  2. "全国年度统计公报".
  3. "全国年度统计公报".
  4. "全国年度统计公报".
  5. "2024年我国大陆核电机组情况".
  6. "全国核电运行情况 (2025年1-9月)".
  7. (2 July 2010). "Nuclear Power in China". World Nuclear Association.
  8. (7 March 2008). ["宁德] 宁德核电站在福鼎开工-图 - 福建之窗 66163.com". Fjnews.66163.com.
  9. (2 November 2021). "China's Climate Goals Hinge on a $440 Billion Nuclear Buildout". Bloomberg.
  10. "China's Climate Goals Hinge on a $440 Billion Nuclear Buildout". Bloomberg.com.
  11. Keith Bradsher. (15 December 2009). "Nuclear Power Expansion in China Stirs Concerns". New York Times.
  12. (31 December 2015). "Chinese firms join forces to market Hualong One abroad". World Nuclear News.
  13. (17 March 2016). "Hualong One joint venture officially launched". World Nuclear News.
  14. (26 February 2020). "The trade war we want China to win: China's nuclear exports can challenge Russian dominance".
  15. (20 June 2019). "China could build 30 'Belt and Road' nuclear reactors by 2030: official". Reuters.
  16. Turner, Ben. (23 July 2021). "China to activate world's first 'clean' nuclear reactor in September".
  17. (27 November 2011). "Summary of China's fast reactor programme".
  18. "Fast Reactor Technology Development for Sustainable Supply of Nuclear Energy in China – China International Nuclear Symposium November 23–25, 2010, Beijing". XU MI – China Institute of Atomic Energy.
  19. "PACIFIC NUCLEAR COUNCIL (PNC) – 2nd QUARTER 2015 MEETING – Thursday, April 23, 2015 – Beijing, CHINA- Meeting Minutes (Final)".
  20. (21 January 2006). "China to build world's first "artificial sun" experimental device". People's Daily Online.
  21. Ambrose Evans-Pritchard, 20 March 2011, [https://www.telegraph.co.uk/finance/comment/ambroseevans_pritchard/8393984/Safe-nuclear-does-exist-and-China-is-leading-the-way-with-thorium.html Safe nuclear does exist, and China is leading the way with thorium] {{Webarchive. link. (25 March 2018 , Telegraph UK)
  22. Chari, P. R.. (1978). "China's Nuclear Posture: An Evaluation". Asian Survey.
  23. Minor, Michael S.. (1976). "China's Nuclear Development Program". Asian Survey.
  24. "Milstone".
  25. "Russian-Chinese Science and Technology Diplomacy and Practice".
  26. "Letter to the Central Committee of the Chinese Communist Party on Not Giving China Samples of Nuclear Weapons and Technical Information".
  27. "Chinese Communist Party Central Committee Decision With Respect To Several Issues Concerning Strengthening Atomic Energy Industrial Infrastructure".
  28. Albright, David. "Chinese Military Plutonium and Highly Enriched Uranium Inventories". Institute for Science and International Security.
  29. "Institute Profile".
  30. "China Nuclear Power".
  31. Daogang Lu (North China Electric Power University). (May 2010). "The Current Status of Chinese Nuclear Power Industry and Its Future". Japan Society of Maintenology.
  32. "Full text of China's Nuclear Emergency Preparedness".
  33. "Daya Bay 1 - World Nuclear Association".
  34. Mann, Jim. (1986-09-22). "China to Build Nuclear Power Plant Despite Hong Kong Safety Fears".
  35. "Full text of China's Nuclear Emergency Preparedness".
  36. Kadak, Andrew C.. (2006). "Nuclear Power: "Made in China"". The Brown Journal of World Affairs.
  37. Massot, Pascale. (2024). "China's Vulnerability Paradox: How the World's Largest Consumer Transformed Global Commodity Markets". [[Oxford University Press]].
  38. Leutert, Wendy. (2024). "China's State-Owned Enterprises: Leadership, Reform, and Internationalization". [[Cambridge University Press]].
  39. (2012-12-23). "China moves to strengthen nuclear safety standards and moderate the pace of its nuclear power development".
  40. (2 October 2025). "Nuclear Power in China". World Nuclear Association.
  41. Yun Zhou. (31 July 2013). "China: The next few years are crucial for nuclear industry growth". Nuclear Engineering International.
  42. (25 March 2014). "Start-up nearing for Chinese units". World Nuclear News.
  43. "Can China Meet Its Nuclear Power Goals?".
  44. (24 February 2020). "China's nuclear power output jumps 18% year on year". World Nuclear News.
  45. "Global Nuclear Power Tracker".
  46. (27 October 2021). "【ACTION PLAN FOR CARBON DIOXIDE PEAKING BEFORE 2030】-National Development and Reform Commission (NDRC) People's Republic of China".
  47. (17 October 2024). "China's nuclear innovation unlocked". Nuclear Engineering International.
  48. Atkinson, Robert D.. (16 September 2024). "China Is Rapidly Becoming a Leading Innovator in Advanced Industries".
  49. (2025-11-26). "World Nuclear Industry Status Report 2025".
  50. (13 October 2025). "PRIS - Reactor status reports - Under Construction - By Country".
  51. (25 September 2025). "The New Nuclear Age: Why the World Is Rethinking Atomic Power". Goldman Sachs.
  52. "Global Nuclear Power Tracker".
  53. (October 2013). "Nuclear Power in China". World Nuclear Association.
  54. (16 March 2011). "China freezes nuclear plant approvals". CNN.
  55. [http://www.channel4.com/news/will-chinas-nuclear-nerves-fuel-a-boom-in-green-energy Will China's nuclear nerves fuel a boom in green energy?] {{Webarchive. link. (21 March 2011 [[Channel 4]], published 17 March 2011. Retrieved 17 March 2011)
  56. some commentators have suggested that additional safety-related costs and public opinion could cause a rethink in favor of an expanded [[Renewable energy in the People's Republic of China. link. (18 March 2011 China Bystander, published 16 March 2011. Retrieved 17 March 2011)
  57. Rob Forrest. (2 June 2014). "China's Nuclear Program and Spent Fuel Storage". CISAC, Stanford University.
  58. (1 September 2017). "China's legislature passes nuclear safety law". Reuters.
  59. (25 May 2023). "Agreements signed during first official visit to China by IAEA's Grossi". Nuclear Engineering International.
  60. "Third Qinshan Nuclear Power Station".
  61. (3 April 2019). "AtomStroyExport unveils schedule for China projects". World Nuclear News.
  62. "First AP1000 unit begins generating power".
  63. (15 October 2019). "Permits issued for construction of new Chinese plant". World Nuclear News.
  64. (29 March 2011). "China forges ahead with nuclear energy". Nature.
  65. "China's commercial reactors". Nuclear Engineering International.
  66. "- Nuclear Power – IAEA".
  67. "Chinese reactor design evolution - Nuclear Engineering International".
  68. (16 July 2010). "First power at China's Ling Ao". Nuclear Engineering International.
  69. (25 November 2010). "China prepares to export reactors". World Nuclear News.
  70. (March 2016). "HPR1000: Advanced Pressurized Water Reactor with Active and Passive Safety". Engineering.
  71. "Nuclear Power in China - World Nuclear Association".
  72. "Chinese reactor design passes safety review - World Nuclear News".
  73. (15 April 2021). "China to begin construction of Hualong Two in 2024 - Nuclear Engineering International".
  74. (15 April 2021). "China to begin construction of Hualong Two in 2024". Nuclear Engineering International.
  75. (14 April 2021). "China to start building Hualong Two nuclear reactor in 2024". Reuters.
  76. (29 September 2020). "China launches CAP1400 reactor design". World Nuclear News.
  77. "China approves construction of six new reactors". www.world-nuclear-news.org.
  78. "Approval for four new reactors in south China". www.world-nuclear-news.org.
  79. (2023-12-06). "China's demonstration HTR-PM enters commercial operation".
  80. (6 December 2023). "Chinese HTR-PM Demo Begins Commercial Operation".
  81. (2024-04-02). "HTR-PM heating project commissioned".
  82. (22 July 2019). "CNNC launches demonstration SMR project". World Nuclear News.
  83. (2 October 2017). "Specific Design Consideration of ACP100 for Application in the Middle East and North Africa Region". CNNC.
  84. (8 June 2021). "China approves construction of demonstration ACP100 – Nuclear Engineering International".
  85. Declan Butler. (21 April 2011). "Reactors, residents and risk". Nature.
  86. (10 August 2017). "Nuclear in China – why the slowdown?". Nuclear Engineering International.
  87. David Stanway, Geert De Clercq. (15 January 2018). "So close yet so far: China deal elusive for France's Areva". Times of Oman.
  88. (1 August 2018). "Nuclear in China – where is it heading now?". Nuclear Engineering International.
  89. (1 June 2020). "China to Dominate Nuclear as Beijing Bets on Homegrown Reactors".
  90. "China Nuclear Power {{!}} Chinese Nuclear Energy – World Nuclear Association".
  91. International Atomic Energy Agency. (2022). "Power Reactor Information System (PRIS): China, People's Republic of". IAEA.
  92. "Construction of new Chinese power plant begins : New Nuclear – World Nuclear News". www.world-nuclear-news.org.
  93. Tony Vince. (8 March 2013). "Rock solid ambitions". Nuclear Engineering International.
  94. (3 January 2011). "China able to reprocess nuclear fuel".
  95. (5 May 2020). "Pinpointing China's new plutonium reprocessing plant".
  96. "China nuclear reprocessing to create stockpiles of weapons-level materials: Experts". The Economic Times.
  97. (25 March 2021). "UPDATE 1-China nuclear reprocessing to create stockpiles of weapons-level materials -experts". Reuters.
  98. "China nuclear reprocessing to create stockpiles of weapons-level materials -experts".
  99. "Current Issues: New Uranium Conversion/Enrichment and Nuclear Fuel Plant Projects - Asia".
  100. "China's Nuclear Fuel Cycle - World Nuclear Association".
  101. (4 November 2016). "Thorium Molten Salt Reactors (TMSR) Development in China".
  102. "中科院与甘肃省签署钍基熔盐堆核能系统项目战略合作框架协议----中国科学院".
  103. "甘肃省公示第四代核能钍基熔盐堆实验平台选址:拟落地武威 _ 东方财富网".
  104. (20 June 2023). "China's experimental molten salt reactor receives licence". Nuclear Engineering International.
  105. Krepel, Jiri. (22 January 2025). "Overview and Update of MSR Activities within GIF".
  106. (14 March 2019). "China signs agreement for nuclear heating demonstration project". Nuclear Engineering International.
  107. (7 September 2018). "CNNC completes design of district heating reactor". World Nuclear News.
  108. (17 February 2012). "China faces civic protests over new nuclear power plants". msn.com.
  109. Calum MacLeod. (16 July 2013). "Protesters win environmental battle in China". USA TODAY.
  110. Lucy Hornby. (26 May 2014). "People power holds key to China's nuclear plans". Financial Times.
Info: Wikipedia Source

This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.

Want to explore this topic further?

Ask Mako anything about Nuclear power in China — get instant answers, deeper analysis, and related topics.

Research with Mako