From Surf Wiki (app.surf) — the open knowledge base
Feroze Gandhi Unchahar Thermal Power Station
Thermal power plant in Raebareli, India
Thermal power plant in Raebareli, India
| Field | Value |
|---|---|
| name | Feroze Gandhi Unchahar Thermal Power Plant |
| image_caption | NTPC Plant |
| coordinates | |
| country | India |
| location | Unchahar, Raebareli, Uttar Pradesh |
| status | O |
| operator | NTPC |
| th_fuel_primary | Coal |
| ps_units_operational | 5 |
| ps_electrical_capacity | 1560.00 MW |
| commissioned | 1988 |
| extra | www.ntpc.co.in |
Feroze Gandhi Unchahar Thermal Power Plant is located at Unchahar in Raebareli district in Indian state of Uttar Pradesh. The power plant is one of the coal based power plants of NTPC Limited. In the year 1992, Uttar Pradesh State Electricity Board (U.P.S.E.B.) transferred Unchahar Thermal Power Station to NTPC Limited against payment overdue and later on renamed it to Feroze Gandhi Unchahar Thermal Power Plant by NTPC Limited.
Description
Feroze Gandhi Unchahar Thermal Power Plant has an installed capacity of 1550 MW, inclusive of Fourth Stage, that got operational in April 2017. The First unit was commissioned in November 1988. The coal for the plant is derived from North Karanpura Coalfield. The water source is from Sarda Sahyak Canal.
Installed capacity
| Stage | Unit Number | Installed Capacity (MW) | Date of Commissioning | Status |
|---|---|---|---|---|
| First | 1 | 210 | 1988 November | Running |
| First | 2 | 210 | 1989 March | Running |
| Second | 3 | 210 | 1999 January | Running |
| Second | 4 | 210 | 1999 October | Running |
| Third | 5 | 210 | 2006 September | Running |
| Fourth & Solar | 6 | 500 ,10 | 2017 April | Running |
2017 Boiler explosion
Main article: 2017 NTPC power plant explosion
A massive explosion ripped a boiler at National Thermal Power Limited (NTPC) Unchahar plant in Uttar Pradesh’s Rae Bareli district on Wednesday, 1 November 2017, killing at least 25 people and injuring nearly 100. The casualties have risen to 32 by Friday. Doctors warned the toll was likely to rise as more than a dozen contractual laborers were battling for life with more than 90 percent burn wounds.
In what is one of the worst industrial disasters in eight years (after Jaipur's Indian Oil fire in 2009), local emergency response was overwhelmed with the scale of disaster. Help was sought from neighboring town and cities including Lucknow and Allahabad. Almost all the injured have been transferred to hospitals in state capital, Lucknow for better treatment.
References
References
- "Power Generation". National Thermal Power Corporation.
- "Coal Based Power Stations". National Thermal Power Corporation.
- "Feroze Gandhi Unchahar Thermal Power Plant". National Thermal Power Corporation.
- (3 April 2017). "BHEL commissions 500 MW unit of NTPC's plant in UP".
- (3 November 2017). "Death toll from NTPC accident increasing. Now 32 dead".
- (2 November 2017). "Major Industrial Accident kills 25 in Uttar Pradesh".
This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.
Ask Mako anything about Feroze Gandhi Unchahar Thermal Power Station — get instant answers, deeper analysis, and related topics.
Research with MakoFree with your Surf account
Create a free account to save articles, ask Mako questions, and organize your research.
Sign up freeThis content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.
Report