From Surf Wiki (app.surf) — the open knowledge base
3 World Trade Center
Office skyscraper in Manhattan, New York
Office skyscraper in Manhattan, New York
| Field | Value |
|---|---|
| name | 3 World Trade Center |
| alternate_names | {{unbulleted list |
| image | Looking up at 3 and 4 World Trade Center (cropped).jpg |
| caption | 3 World Trade Center in September 2019 |
| location | 175 Greenwich Street, Manhattan, New York City 10007 |
| mapframe-wikidata | yes |
| coordinates | |
| start_date | March 8, 2010 |
| completion_date | 2018 |
| architect | Rogers Stirk Harbour + Partners, AAI Architects, P.C. (as architect of record) |
| owner | Port Authority of New York and New Jersey |
| cost | |
| floor_area | 2232984 sqft |
| floor_count | 80 |
| references | |
| building_type | Office, Retail |
| architectural_style | Modern |
| height | 1079 ft |
| elevator_count | 53 |
| structural_engineer | WSP Cantor Seinuk |
| main_contractor | Tishman Construction |
| status | Complete |
| opened | June 11, 2018 |
| developer | Silverstein Properties |
| engineer | {{ubl |
the current skyscraper in Lower Manhattan
|3 WTC |175 Greenwich Street | mapframe-wikidata = yes Weidlinger Associates (Peer Review) |Jaros, Baum & Bolles (MEP, Vertical Transportation) |Fisher Marantz Stone (Lighting) |Permasteelisa Group (Facade) 3 World Trade Center (3 WTC; also known as 175 Greenwich Street) is a skyscraper constructed as part of the new World Trade Center in Lower Manhattan, New York City. The tower is located on Greenwich Street along the eastern side of the World Trade Center site. The building was designed by Rogers Stirk Harbour + Partners, and is managed by Silverstein Properties through a ground lease with the Port Authority of New York and New Jersey (PANYNJ), the landowner. It is 1079 ft high, with 80 stories. , it is the tenth-tallest building in the city.
The current edifice is the second on the World Trade Center site to bear the address 3 World Trade Center. The original building was the Marriott World Trade Center, a 22-story, 825-room hotel located in the southwest corner of the World Trade Center complex. Opened in July 1981 as the Vista International Hotel, it was destroyed during the September 11 attacks in 2001, along with the rest of the World Trade Center.
The current 3 World Trade Center was planned as a skyscraper measuring 1,240 feet (378 m) tall. The building's groundbreaking took place in January 2008, but only the lower stories were built because the skyscraper lacked an anchor tenant. Construction resumed in 2014 after advertising company GroupM was signed on as anchor tenant. The building's concrete core was topped out during August 2016, with the perimeter steel structure following on October 6, 2016. The building opened on June 11, 2018.
Site
Main article: World Trade Center site
3 World Trade Center is at 175 Greenwich Street, within the new World Trade Center (WTC) complex, in the Financial District neighborhood of Lower Manhattan in New York City. The land lot is bounded by Greenwich Street to the west, Dey Street to the north, Church Street to the east, and Cortlandt Way to the south. Within the World Trade Center complex, nearby structures include the National September 11 Memorial & Museum to the west; One World Trade Center to the northwest; World Trade Center Transportation Hub and 2 World Trade Center to the north; and 4 World Trade Center to the south. Outside World Trade Center, nearby buildings include 195 Broadway and the Millennium Hilton New York Downtown hotel to the northeast, as well as One Liberty Plaza to the southeast.
Previous buildings
For most of the 20th century, the site of 3 WTC was occupied by the Cortlandt Building, built in 1907 and one of two office structures that comprised the Hudson Terminal complex. The site was also abutted by several low-rise buildings on Greenwich Street to the west. During the late 19th and early 20th centuries, the adjoining section of Cortlandt Street had been part of Manhattan's Radio Row, which contained many electronics stores. The Hudson Terminal complex was demolished in 1972, when the original World Trade Center was built.
The Port Authority of New York and New Jersey (PANYNJ), which was responsible for the construction of the World Trade Center, had demolished several streets to make way for the towers within the World Trade Center, including parts of Cortlandt, Dey, and Greenwich Streets. The site of the current skyscraper was occupied by 5 World Trade Center at the northeast corner of the World Trade Center site. Terrorists destroyed the World Trade Center during the September 11 attacks. Greenwich Street was restored as part of the redevelopment of the World Trade Center, and the block of Cortlandt Street next to 3 WTC was rebuilt as a pedestrian walkway. The intersection of Cortlandt Way and Greenwich Street reopened in 2014, improving access to the National September 11 Memorial.
The 3 World Trade Center address was originally used by the Marriott World Trade Center (originally the Vista International Hotel), a 22-story hotel building with 825 rooms. Construction began in 1979, The hotel was heavily damaged in the 1993 World Trade Center bombing and reopened in 1994 after repairs. The Host Marriott Corporation acquired the hotel in 1995 for $141.5 million. Forty people in the hotel died when the complex was destroyed during the September 11 attacks. Marriott, which held a long-term lease on the hotel site, surrendered its lease in 2003, allowing the National September 11 Memorial & Museum to be built there.
History
Site redevelopment
Larry Silverstein had leased the original World Trade Center from the PANYNJ in July 2001. His company Silverstein Properties continued to pay rent on the site even after the September 11 attacks. In the months following the attacks, architects and urban planning experts held meetings and forums to discuss ideas for rebuilding the site. The architect Daniel Libeskind won a competition to design the master plan for the new World Trade Center in February 2003. The master plan included five towers, a 9/11 memorial, and a transportation hub. By July 2004, two towers were planned on the southeast corner of the site: the 62-story 3 World Trade Center and the 58-story 4 World Trade Center. The plans were delayed due to disputes over who would redevelop the five towers. The PANYNJ and Silverstein ultimately reached an agreement in 2006. Silverstein Properties ceded the rights to develop 1 and 5 WTC in exchange for financing with Liberty Bonds for 2, 3, and 4 WTC.
British architect Richard Rogers of Rogers Stirk Harbour + Partners was hired to design the new 3 World Trade Center, on the eastern part of the World Trade Center site at 175 Greenwich Street, in May 2006. Additionally, Norman Foster and Fumihiko Maki were selected as the architects for 2 and 4 World Trade Center, respectively. The plans for 2, 3, and 4 World Trade Center were announced in September 2006. 3 World Trade Center would be a 71-story, 1155 ft building with diagonal bracing on its facade for structural reinforcement. The tentative plans also called for four spires, one at each corner, rising 100 ft above the flat roof. The building would have contained 133,000 ft2 of retail space in its base; five trading floors; and 2.1 e6ft2 of offices across 54 stories. The lowest stories of 3 World Trade Center and several neighboring buildings would be part of a rebuilt Westfield World Trade Center Mall.
As part of the project, Cortlandt Street (which had been closed to make way for the original World Trade Center) was planned to be rebuilt between 3 and 4 WTC. The plans for Cortlandt Street affected the design of the lower stories of both 3 and 4 WTC, as one of the proposals called for an enclosed shopping atrium along the path of Cortlandt Street, connecting the two buildings. The street was eventually rebuilt as an outdoor path. Final designs for 2, 3, and 4 WTC were announced in September 2007. The three buildings would comprise the commercial eastern portion of the new World Trade Center, contrasting with the memorial in the complex's western section. At the time, construction of 3 WTC was planned to begin in January 2008. As part of its agreement with the PANYNJ, Silverstein Properties was obliged to complete 3 and 4 WTC by the end of 2011.
Construction
Initial construction and disputes
Investment bank Merrill Lynch & Co. expressed interest in relocating its headquarters to 3 World Trade Center in mid-2008. Following this, the PANYNJ voted to extend the deadline for the building's completion to June 2012. Merrill had been the first private firm to show interest in leasing significant amounts of space at the World Trade Center, and the announcement raised the possibility that 3 WTC could be redesigned for Merrill's use. The PANYNJ offered to lease the underlying land to Merrill for $510 million, 25 percent lower than the agency's original asking price for the land, and Silverstein offered to sell his stake in the project for $340 million. Merrill balked at Silverstein's offer, and it withdrew from the project in July 2008 after failing to secure a lease on favorable terms. Merrill's withdrawal came shortly after the PANYNJ had announced that the World Trade Center redevelopment would be delayed significantly. Meanwhile, police officials expressed concern that the building's all-glass design posed a security risk. A study published in early 2009 predicted that 3 WTC would not be fully occupied until 2037, due to the 2008 financial crisis.
By May 2009, the PANYNJ was seeking to reduce the size of 2 and 3 WTC and postpone the construction of 5 WTC, citing the Great Recession and disagreements with Silverstein. The developer had requested that the PANYNJ fund two of the towers, but the agency wanted to take control of the 3 WTC site and was willing to provide funding for only one tower. The PANYNJ wanted to build 3 WTC only to the fourth story, allowing Silverstein to construct a hotel or office building above when market conditions improved. New York City mayor Michael Bloomberg attempted to mediate the dispute with little success. In July 2009, Silverstein wrote a letter to the development's stakeholders, recommending that the dispute go to arbitration. Silverstein officially requested arbitration the next month. He requested that the PANYNJ pay $2.7 billion in damages. An arbitration panel ruled in January 2010 that the agency did not owe him any damages. However, the panel also voided a clause that would have forced Silverstein to hand over the towers to PANYNJ if they were not completed by 2014. The panel gave Silverstein and the PANYNJ two months to reach an agreement.
As part of the arbitration process, Silverstein requested a $2.6 billion tax-free bond issue for the redevelopment of the World Trade Center site. The New York state government approved the bond issue in December 2009, though the construction of 2 and 3 WTC remained on hold. In February 2010, Silverstein proposed constructing 3 WTC and delaying plans for 2 WTC, a move that was expected to save $262 million in the short term. The next month, the PANYNJ and the city and state governments of New York agreed to fund $600 million for 3 WTC's construction after Silverstein had found tenants for at least 40000 ft2 of the space. Silverstein would build the first five stories by 2013 if he were unable to finance the project and lease the office space. PANYNJ board members from New Jersey acquiesced to the deal with Silverstein, but only on the condition that the agency also fund a reconstruction of the Bayonne Bridge.
Three PureCell fuel cells were delivered at the World Trade Center site in November 2010, providing about 30 percent of 3 WTC's power. In the meantime, the 1137 ft tower had been delayed indefinitely. The investment bank UBS was considering leasing space at 3 WTC in mid-2011 but ultimately decided against it. At the time, although the complex was originally supposed to have been anchored by large financial firms, these companies were generally no longer seeking to expand their space.
Funding compromise and anchor tenant
Silverstein Properties and the PANYNJ agreed in early 2012 to complete only the first seven stories of 3 WTC unless tenants could be found by the end of the year. The base had been built entirely with insurance proceeds, and the tower stories would only be built after Silverstein met the requirements. By that February, the ground floor concrete was almost done and the lower podium had reached the 5th floor; the podium was then planned to be completed in September 2012. Owen Steel's president David Zalesne announced in June 2012 that his company had been selected to provide the structural steel for the building. The next month, the concrete core had reached the 8th floor, and all concrete work had halted. Media conglomerate Viacom and financial firm Citigroup had both declined to relocate to 3 WTC. The lower podium was completed by November 2012. If Silverstein were unable to finalize a lease by the end of 2013, he would have been required to build a semi-permanent roof above the 7th story.
By late 2012, advertising company GroupM was negotiating to lease 550000 ft2 at 3 WTC, and law firm White & Case was looking for about 500,000 ft2. Either of these deals would be large enough to qualify the project for up to $600 million in public benefits. GroupM signed a letter of intent for the building in mid-2013, and the company finalized its lease that December, taking 500000 ft2. The following month, U.S. senator Chuck Schumer obtained $340 million in federal Recovery Zone bonds to finance the project's construction.
Silverstein asked the city, state, and PANYNJ in 2014 to refinance the project on terms that were more favorable to him. In exchange, he would contribute a greater share of private capital. The PANYNJ postponed a vote on whether to guarantee $1.2 billion of construction loans in March 2014, and the vote was delayed again that April. Although PANYNJ chairman Scott Rechler supported the subsidy, other PANYNJ board members said the guarantee was wasteful because the majority of the proposed building still did not have tenant commitments. The PANYNJ voted against guaranteeing the construction loans in May 2014, but the PANYNJ and Silverstein reached a financing agreement the next month. The large amount of unleased space made it difficult for Silverstein to sell bonds to private investors, so the building was instead mainly funded by the sale of $1.6 billion of tax-exempt bonds, the largest-ever unrated bond deal in the municipal bond market. Other sources of funding included $600 million in insurance proceeds, $210 million in cash from the city and state governments of New York, and $55 million in cash from Silverstein Properties. Silverstein sold the municipal bonds at the end of October 2014.
Resumption of construction
Following the financing agreement, the tower crane returned, and the PANYNJ and Silverstein announced that the building would be completed by 2017. Unusual for a high-rise, the building's concrete core was built before the rest of the structure was completed. Fintech company Fundrise sold $5 million of the building's municipal bonds to private investors in January 2015. Work above the second story had begun by the next month. That June, the architects eliminated the planned rooftop masts, reduced the building to its final height of 1,079 ft. Nonetheless, by August 2015, the building had reached half of its final height. The construction process was complicated by the fact that water started leaking into the construction site in late 2015, delaying the opening of the adjacent Westfield World Trade Center mall. The site was completely exposed to the outdoors, and workers were constantly spraying water onto the building's concrete to decrease dust levels, both of which caused water to seep into the building.
On May 20, 2016, the tower's concrete core reached the symbolic height of 1,000 ft, thus officially reaching supertall status and exceeding the roof height of neighboring 4 World Trade Center. 3 World Trade Center's core was topped out one month later on June 23, 2016. In a ceremony held at the base of the building, a 2-ton bucket of concrete was signed by workers, and executives, including developer Larry Silverstein, and was hoisted up with an American flag, which was also used with the topping out of 7 and 4 World Trade Center, to the top of the tower.
On the evening of August 11, 2016, a construction crane struck one of 3 World Trade Center's windows. There was a heavy wind gust at the time, and construction workers were securing the crane when it veered into a 12th-story glass panel, cracking it. No one was injured. On October 6, 2016, the entire building was topped out when the last steel beam was lifted and installed on top. The glass facade was completed in August 2017, at which point several retailers had signed leases for the atrium retail space. File:WTC 3-April 2014.jpg|Construction of 3 World Trade Center as of April 2014 File:Three World Trade Center New York NY 2015 06 10 09.jpg|3 World Trade Center under construction on June 10, 2015. The PATH station is visible to the right. File:3-4 World Trade Center at night 2016.JPG|The PATH Station, 3, and 4 World Trade Center at night in May 2016 File:Three World Trade Center topping out ceremony.png|Developer Larry Silverstein and construction workers sign the last bucket of concrete during the topping-off ceremony on June 23, 2016. File:3 World Trade Jan 2017.png|3 World Trade Center under construction on January 26, 2017 File:3-4 World Trade Center 2017.jpg|3 World Trade Center under construction on May 8, 2017
Opening and early years
3 WTC's anchor tenant GroupM had expanded its space to 700000 ft2 in January 2016, and GroupM hired the architectural firm to redesign 15 floors in the building for its nine constituent companies. The stock exchange platform IEX leased 45000 ft2 in the building in April 2018. This was followed the next month by global consulting company McKinsey & Company, which leased 186000 ft2. The building officially opened on June 11, 2018. At the time, the building was 38 percent occupied.
In the first three months of 2019, Silverstein leased space to Hudson River Trading, Casper Sleep, beverage firm Diageo, technology startup Asana Inc., and mortgage lender Better.com. These five leases totaled 355000 ft2. Later that year, ridesharing company Uber leased more than 300000 ft2, and law firms Kelley Drye & Warren and Cozen O'Connor also leased space there. Private equity firm Blue Wolf Capital Partners leased space in early 2020, and Uber sought to sublease some of its space by the end of that year. Casper subleased some of its space to advertising company Index Exchange in 2021. In addition, the law firm Freshfields Bruckhaus Deringer leased four stories at 3 WTC in August 2022.
Architecture
3 World Trade Center was designed by Richard Rogers of Rogers Stirk Harbour + Partners. The structural engineer for the building was WSP Global. It is 1,079 ft tall with 80 above-ground stories. The lowest 17 stories of the tower comprise a podium. There are five stories of retail, spanning the basement and sub-basement levels as well as the first three above-ground stories.
Facade

The facade is composed of double-glazed, low emissivity glass panels. Most of the facade is a curtain wall with 10,000 panels of annealed glass, which are more resistant to shattering compared with traditional glass panels. The curtain wall panels span from the floor to the ceiling on each story. They measure 13.5 ft high on each of the podium stories and 24 ft high on each of the tower stories. At the base of the building, a cable-net wall surrounds the lobby on three sides. The cable-net wall is composed of panels measuring 5 ft wide and 10 ft tall.
The eastern and western elevations of the facade contain K-shaped bracing, which is composed of diagonal beams clad in stainless steel. The diagonal beams reinforce the superstructure and remove the need for structural columns at the corner. The stainless steel cladding is used to protect the beams from weathering, and it was also intended to complement the glass panels on the facade. The roof of the building is flat, though originally it was planned with several spires.
Features
3 World Trade Center covers 2.5 e6ft2 in total. Each of the building's stories spans 30000 to. The building uses 27000 ST of steel and 145000 yd3 of concrete. 3 WTC also includes 44 passenger elevators and five service elevators. Four of the service elevators are also specifically designed to be used for emergency evacuations. Eight of the passenger elevators serve the first 17 stories exclusively, and there are two passenger and two service elevators within the retail section of the building. There are also four staircases within the podium and two staircases within the upper stories.
Lobby and retail
There are nine entrances to 3 WTC's lobby. The floor of the lobby is made of Sardinian gray granite. The western wall of the lobby is made of Zimbabwe black granite and measures 43 ft high. The walls of the elevator banks contain glass panels with a metallic mesh embedded into them. There are also LED wall panels next to the elevators themselves. The lobby's ceiling measures up to 62 ft high, though it slopes down to as low as 22 ft. The ceiling is made of a stretched material, behind which are LED lights; at the time of 3 WTC's opening, this was the largest stretched ceiling in the world.
One wall of the lobby contains Joystick, a 46 ft mural by James Rosenquist, which was originally painted in 2002 and reinstalled at 3 WTC in 2020. Untitled (Fish on Fire, Greenwich Street) 2024, a copper sculpture by Frank Gehry, has been mounted in the lobby of 3 WTC since 2025. The sculpture, measuring 20 by across, can rotate and is illuminated from inside.
The rest of the ground, second, and third stories are used as retail space. There are two basement levels, which also contain retail and are part of Westfield World Trade Center mall. The five retail stories are connected by two passenger elevators and four staircases. The mall connects to the World Trade Center Transportation Hub, which in turn links with the New York City Subway and PATH trains.
Upper stories
The building has ceiling heights ranging from 13 to. There are terraces wrapping around 3 World Trade Center on floors 17, 60, and 76. The terrace on floor 17 is 205 ft high and is divided into two sections, each measuring 5500 ft2. One of the terraces on floor 17 is shared by all of the building's tenants, while the other is a private terrace. The terrace on floor 17 was originally designed as a mechanical area with space for financial companies' equipment, but this was scrapped when GroupM became the building's anchor tenant. The terrace on floor 60 is 718 ft high, while that on floor 76 is 934 ft high.
The air-conditioning systems on each story are controlled separately, thus reducing energy consumption. In addition, the building's filtration systems are able to extract 95 percent of particulates, in addition to ozone and volatile organic compounds. The building contains air intake openings on its upper stories, since the air on higher stories was supposed to be cleaner than the air near ground level. Jaros, Baum & Bolles installed the mechanical, electrical, and plumbing system.
Critical reception
When 3 WTC was completed in 2018, James Gardner of The Real Deal New York wrote: "I can say with reasonable confidence that it will prove to be the least architecturally interesting of the four main buildings on the hallowed site." In particular, Gardner criticized "the arbitrary asymmetries, the industrial aesthetic in one part but not another, the shift in cladding patterns" in the design.
References
Notes
Sources
References
- {{Ctbuh. 273. Three World Trade Center
- "Emporis building ID 252968". [[Emporis]].
- {{skyscraperpage. 7802
- {{structurae. 20010237
- GmbH, Emporis. "Three World Trade Center, New York City {{!}} 252968 {{!}} EMPORIS".
- "12 tallest skyscrapers in New York City". am New York.
- (May 6, 2019). "The World Trade Center".
- "185 Greenwich Street, 10007". [[New York City Department of City Planning]].
- {{cite aia5
- (April 3, 1907). "A $5,000,000 Tunnel Station". New-York Tribune.
- Condit, C.W.. (1980). "The Port of New York: A history of the rail terminal system from the beginnings to Pennsylvania Station". University of Chicago Press.
- Dunlap, David W.. (August 1, 2014). "At World Trade Center Site, Rebuilding Recreates Intersection of Long Ago". The New York Times.
- (December 10, 1972). "College Works With Firemen in Safety Test". New York Daily News.
- "The World Trade Center Complex". [[Port Authority of New York and New Jersey]].
- Gillespie, Angus K.. (1999). "Twin Towers: The Life of New York City's World Trade Center". [[Rutgers University Press]].
- (July 27, 2004). "The 9/11 Commission Report". [[9/11 Commission.
- Satow, Julie. (July 18, 2012). "Sundered Greenwich Street Will Be Rejoined". The New York Times.
- Dunlap, David W.. (October 25, 2012). "Missing for 50 Years, a Bit of Cortlandt Street Will Return".
- Ferretti, Fred. (December 12, 1979). "At Trade Center, a Hotel Rises". The New York Times.
- (June 30, 1981). "Fred R. Conrad Vista International Hotel to Officially Open Its Doors Tomorrow". The New York Times.
- McKinley, James C. Jr.. (March 15, 1993). "Vista Hotel Is Closed Until Summer, Officials Say". The New York Times.
- Deutsch, Claudia H.. (October 31, 1994). "20 Months After Bombing, Vista Hotel to Finally Reopen". The New York Times.
- (November 10, 1995). "Port Authority Sells Hotel". The New York Times.
- (September 11, 2002). "One Hotel's Fight to the Finish; At the Marriott, a Portal to Safety as the Towers Fell". The New York Times.
- Dunlap, David W.. (October 24, 2003). "Marriott Ceding Property Where Hotel Stood on the World Trade Center Site". The New York Times.
- (July 4, 2004). "A Status Report: As Lower Manhattan Rebuilds, a New Map Takes Shape". The New York Times.
- Smothers, Ronald. (July 25, 2001). "Leasing of Trade Center May Help Transit Projects, Pataki Says". The New York Times.
- Bagli, Charles V.. (November 22, 2003). "Silverstein Will Get Most of His Cash Back In Trade Center Deal". The New York Times.
- McGuigan, Cathleen. (November 12, 2001). "Up From The Ashes".
- Libeskind, Daniel. (2004). "Breaking Ground". [[Riverhead Books]].
- Wyatt, Edward. (February 27, 2003). "Libeskind Design Chosen for Rebuilding at Ground Zero". The New York Times.
- Frangos, Alex. (2004-10-20). "Uncertainties Soar At Ground Zero". Wall Street Journal.
- Satow, Julie. (20 Feb 2006). "Ground Zero Showdown: Freedom Tower puts downtown in bind".
- Dunlap, David W.. (April 28, 2006). "Freedom Tower Construction Starts After the Beginning". The New York Times.
- Todorovich, Petra. (March 24, 2006). "At the Heart of Ground Zero Renegotiations, a 1,776-Foot Stumbling Block". Regional Plan Association.
- Pogrebin, Robin. (May 3, 2006). "Richard Rogers to Design Tower at Ground Zero". The New York Times.
- (Jun 2006). "Rogers, Maki to design towers at Ground Zero".
- Frangos, Alex. (May 18, 2006). "Triplet Towers". Wall Street Journal.
- Dunlap, David W.. (September 8, 2006). "A First Look at Freedom Tower's Neighbors". The New York Times.
- Chung, Jen. (September 7, 2006). "Vision of World Trade Center in the Future".
- (September 7, 2006). "Designs for three World Trade Center Towers Unveiled". Lower Manhattan Development Corporation.
- Frangos, Alex. (September 8, 2006). "Plans for Three Trade Center Towers Are Unveiled; Details Need to Be Finalized For Designs and Outlays; 'Beacon,' Spires, Simplicity". Wall Street Journal.
- Hudson, Kris. (January 17, 2008). "At Ground Zero, Optimism Returns". Wall Street Journal.
- Dunlap, David W.. (November 24, 2005). "Does Putting Up a Glass Galleria Count as Bringing Back a Street?". The New York Times.
- Dunlap, David W.. (July 6, 2006). "Debating the Path of Cortlandt Street". The New York Times.
- (September 7, 2007). "WTC tower sketches are pictures of safety".
- Chan, Sewell. (September 6, 2007). "Activity Picks Up as 9/11 Anniversary Approaches".
- Dunlap, David W.. (September 7, 2007). "Developers Unveil Plans for Trade Center Site". The New York Times.
- Drury, Allan. (September 11, 2007). "Ground Zero rebuilding may finally be moving". The Journal News.
- Bagli, Charles V.. (May 23, 2008). "Merrill Lynch Weighs Putting Headquarters at Ground Zero". The New York Times.
- Collins, Glenn. (January 13, 2008). "Between Rock and the River, the Going Is Slow, and Costly". The New York Times.
- Dunlap, David W.. (January 24, 2007). "One Steel Cage Up, and Many More to Follow". The New York Times.
- (January 10, 2008). "Port misses deadline and says 'worst' construction noise is almost over". amNewYork.
- (February 20, 2008). "WTC Site Construction Update, February 2008".
- Dupré, Judith. (2016). "One World Trade Center: Biography of the Building". Little, Brown.
- Collins, Glenn. (February 20, 2008). "Work on Site at Trade Center Is Completed 48 Days Late". The New York Times.
- Frangos, Alex. (May 22, 2008). "Merrill Restarts Talks to Move Base to World Trade Center Site; Firm Is One of Few In Private Sector To Express Interest". Wall Street Journal.
- Arak, Joey. (May 22, 2008). "Freedom's Friends Delayed, But Tower 3 May Get Lynch'd".
- Bagli, Charles V.. (July 17, 2008). "Merrill Lynch Ends Talks on Moving to Ground Zero". The New York Times.
- Frangos, Alex. (June 30, 2008). "Trade Center Rebuilding Faces Big Setback". Wall Street Journal.
- (July 17, 2008). "Merrill Lynch ends World Trade Center talks-report".
- Clark, Ryan. (July 17, 2008). "Merrill Lynch Abandons WTC".
- Smith, Greg B.. (February 24, 2008). "Pros fear new towers at World Trade Center site have security gaps".
- Gralla, Joan. (April 16, 2009). "World Trade Center rebuild faces decades of delays".
- (May 11, 2009). "Port Authority wants to dump three of five proposed skyscrapers for WTC site".
- Agovino, Theresa. (May 18, 2009). "Port Authority vs. Silverstein feud heads to Gracie Mansion".
- (July 18, 2009). "Trade Center Developer and Port Authority at Odds Again". [[The New York Times]].
- Chung, Jen. (May 21, 2009). "What WTC Towers 2 And 3 Look Like As Low-Rises".
- Bagli, Charles V.. (June 9, 2009). "Little Progress Is Seen in Talks on Ground Zero". The New York Times.
- Bagli, Charles V.. (July 7, 2009). "Port Authority Is Blamed for Trade Center Delays". The New York Times.
- Brown, Eliot. (July 6, 2009). "Silverstein Goes to the Mattresses! Takes Legal Action To End WTC Stalemate".
- (August 13, 2009). "Agency report supports Silverstein in World Trade Center dispute". amNewYork.
- Bagli, Charles V.. (August 5, 2009). "Developer at Ground Zero Seeks Arbitration". The New York Times.
- Bagli, Charles V.. (January 27, 2010). "Trade Center Site Developer Set Back". The New York Times.
- Polsky, Sara. (January 27, 2010). "Arbitration Panel Awards Zero Dollars to Silverstein for WTC".
- Bagli, Charles V.. (March 5, 2010). "Trade Center Financing Rift Still Wide as Deadline Nears". The New York Times.
- Brown, Eliot. (November 18, 2009). "Silverstein Wants $2.6 B. in WTC Bonds—But for What?".
- Gralla, Joan. "NY agency OKs tax-free debt for World Trade Center".
- Chung, Jen. (February 19, 2010). "Silverstein Proposes To Forget World Trade Center Tower 2".
- (March 26, 2010). "World Trade Center developer Larry Silverstein and Port Authority reach deal for two new towers".
- (March 26, 2010). "Tentative WTC site deal reached Three office towers to be built as per agreement Details to be worked out over next 4 months". Newsday.
- Bagli, Charles V.. (March 26, 2010). "Tentative Deal Struck for 2 Ground Zero Towers". The New York Times.
- Feiden, Douglas. (September 15, 2010). "New Jersey politicians strike back-room deal with Port Authority for Bayonne Bridge, WTC funding".
- Clark, Ryan. (August 26, 2010). "Bayonne Bridge, WTC Barter a Done Deal".
- Troianovski, Anton. (November 1, 2010). "WTC Taps Fuel Cells". Wall Street Journal.
- (May 5, 2011). "When Barack Obama returns to World Trade Center site, he'll see marked construction progress".
- Bagli, Charles V.. (June 8, 2011). "Regretting Move, Bank May Return to Manhattan". The New York Times.
- Brown, Eliot. (June 20, 2011). "Banks Search for City Space". Wall Street Journal.
- Brown, Eliot. (September 10, 2011). "After the Fall, World Trade Center Rises as Memorial and Workplace: A Twisting Path For Developer And New York". Wall Street Journal.
- (July 29, 2011). "UBS Said to End Talks to Move to NYC's World Trade Center".
- Brown, Eliot. (July 9, 2013). "World Trade Center Tower May Rise After New Tenant Signs". Wall Street Journal.
- Rosen, Daniel Edward. (January 23, 2012). "3 World Trade Center Gambit: Silverstein Could Cut Tower Short".
- (January 23, 2012). "Incredible Shrinking Building Long Story Short: Econ Takes Bite Outta 3 WTC". New York Daily News.
- (September 8, 2006). "Lower Manhattan : 3 World Trade Center (175 Greenwich Street)". Lowermanhattan.info.
- "Business Notebook – Business". TheState.com.
- Brown, Eliot. (July 25, 2012). "New Hitch In Ground Zero Plans: No Takers". Wall Street Journal.
- Cameron, Christopher. (July 25, 2012). "WTC complex progress stalls amid slow office leasing environment".
- (November 15, 2012). "WTC Construction Update, November 2012".
- Geiger, Daniel. (October 2, 2012). "GroupM Considers Huge Lease to Anchor 3 WTC".
- (October 3, 2012). "Group M | 3 WTC | Silverstein Properties".
- (December 5, 2012). "Silverstein Said Moving Toward Two Deals at Trade Center".
- Cameron, Christopher. (December 5, 2012). "Advertising agency, law firm in lease talks at 3 WTC".
- Samtani, Hiten. (July 9, 2013). "3 WTC".
- Morris, Keiko. (December 24, 2013). "Ad Firm Group M Leases At WTC". Wall Street Journal.
- Chaban, Matt. (December 23, 2013). "GroupM signs long lease with Larry Silverstein so 3 World Trade Center can move forward".
- (January 13, 2014). "3 WTC snags $340M in financing from state program".
- Alberts, Hana R.. (January 13, 2014). "3 World Trade Gets Crucial Financing To Rise With Confidence".
- (January 29, 2014). "Silverstein Seeks New Debt Deal for WTC Complex". Wall Street Journal.
- (January 29, 2014). "Silverstein wants refi for stalled 3 World Trade Center".
- (March 19, 2014). "Port Authority to Vote Next Month on WTC Tower Financing".
- Bagli, Charles V.. (March 20, 2014). "Vote Put Off on Trade Center Loan". The New York Times.
- (April 23, 2014). "Port Authority Board Puts Off Vote On Loan For 3 World Trade Center".
- (April 23, 2014). "Port Authority Again Delays Vote on 80-Story Tower at World Trade Center Site". The New York Times.
- Bagli, Charles V.. (March 17, 2014). "Developer's Skyscraper Is Focus of Latest Dispute at Rebuilt Trade Center". The New York Times.
- (May 29, 2014). "3 World Trade Center Financial Package Delayed". Wall Street Journal.
- Dailey, Jessica. (June 23, 2014). "Yet Another Financing Deal Floated for 3 World Trade Center".
- (October 21, 2014). "World Trade Center Tower Rides a Muni-Bond Revival". Wall Street Journal.
- Ghigliotty, Damian. (November 28, 2014). "With 3 WTC Financing Finally a Done Deal, What Comes Next?". Commercial Observer.
- Clarke, Katherine. (October 29, 2014). "New tower to rise at 3 WTC". New York Daily News.
- (October 28, 2014). "World Trade Center Tower Set to Rise After $1.6 Billion Bond Deal". Wall Street Journal.
- Porter, Dave. (June 25, 2014). "Deal Reached to Finish 3 World Trade Center Tower".
- Dunlap, David W.. (May 25, 2016). "Skyscraper at Trade Center Rises From the Inside Out". The New York Times.
- Clarke, Katherine. (January 27, 2015). "Investors can snag a stake in 3 World Trade Center for just $5,000 with new crowd funding initiative".
- Alberts, Hana R.. (February 27, 2015). "Glory Be, 3 World Trade Center Finally Started Rising Again".
- (February 27, 2015). "World Trade Center Site".
- YIMBY, New York. (August 12, 2015). "Three World Trade Center Gets Height Cut, Will Stand 1,079 Feet Tall". New York YIMBY.
- Alberts, Hana R.. (June 23, 2015). "3 World Trade Center Tweaks Design, Drops Rooftop 'Masts'".
- Rosenberg, Zoe. (August 7, 2015). "3 World Trade Center Now Stands at Half of Its Final Height".
- (August 7, 2015). "Construction Update: 175 Greenwich Street aka Three World Trade Center Reaches Halfway Point".
- Dunlap, David W.. (November 4, 2015). "Another Setback for World Trade Center Transit Hub: Leaking Water". The New York Times.
- (November 9, 2015). "ICYMI".
- "3 World Trade Center Reaches Supertall Territory".
- Warerkar, Tanay. (June 24, 2016). "3 World Trade Center finally tops out at 1,079 Feet".
- (June 23, 2016). "3 World Trade Center Marks Milestone With Topping Out Ceremony".
- (August 12, 2016). "Crane accident smashes 12th-story window at WTC".
- Bowerman, Mary. (August 12, 2016). "Crane breaks window at 3 World Trade Center".
- Warerkar, Tanay. (June 24, 2016). "3 World Trade Center finally tops out at 1,079 Feet".
- Warerkar, Tanay. (August 1, 2017). "3 World Trade Center nears the finish line in the Financial District".
- Katz, Rayna. (January 5, 2016). "GroupM Expands at 3 World Trade Center".
- Baird-Remba, Rebecca. (January 29, 2019). "How GroupM Created an Office in 3 WTC for Nine Different Companies".
- Mashayekhi, Rey. (April 4, 2018). "Stock exchange IEX leases 45,000 s/f at 3 WTC".
- Guerre, Liam La. (May 16, 2018). "McKinsey & Company to Relocate HQ From Midtown East to 3 WTC".
- Matthews, Karen. (June 10, 2018). "New World Trade Center to open after years of delays".
- (June 11, 2018). "3 World Trade Center office building set to open after years of delays".
- Kim, Betsy. (January 7, 2019). "Fintech firm to double space, swap buildings at World Trade Center".
- Baird-Remba, Rebecca. (January 7, 2019). "Casper Leaves Midtown South for World Trade Center".
- Jordan, John. (January 11, 2019). "Diageo to Move Primary North America Operations to 3 World Trade".
- (March 14, 2019). "Better.com takes 44,000 s/f at 3 World Trade Center".
- Kim, Betsy. (March 15, 2019). "Home Mortgage Company Better.com Leases at 3 WTC".
- Baird-Remba, Rebecca. (October 23, 2019). "Uber Signs at 3 WTC for Space Topping 300K SF".
- Rizzi, Nicholas. (September 4, 2019). "Law Firm Kelley Drye & Warren Takes 103K SF at 3 World Trade Center".
- Baird-Remba, Rebecca. (February 20, 2020). "Blue Wolf Capital Heads to 3 WTC".
- (November 6, 2020). "Uber Could Sublet 25% of 3 World Trade Center Office".
- Young, Celia. (November 19, 2021). "Advertising Firm Index Exchange Takes Casper Sleep's Offices at 3 WTC".
- Tunberg, Ingrid. (August 24, 2022). "3 World Trade Secures New 180K-SF Lease".
- Rosenberg, Zoe. (January 27, 2017). "3 World Trade Center's glass facade has come a long way". Curbed NY.
- Fazzare, Elizabeth. (June 11, 2018). "Architect Richard Rogers Hopes 3 World Trade Center Will Help Create a "People's Place"".
- "Ground Zero Office Designs Hailed as Hopeful Symbols" ''Engineering News-Record'', September 18, 2006, pg. 12
- Warerkar, Tanay. (June 7, 2018). "3 WTC, NYC's fifth tallest tower, debuts".
- Clark, Roger. (June 11, 2018). "3 World Trade Center high-rise tower opens".
- {{harvnb. Fact Sheet. 2019
- {{harvnb. Fact Sheet. 2019
- {{harvnb. Fact Sheet. 2019
- {{harvnb. Fact Sheet. 2019
- {{harvnb. Fact Sheet. 2019
- Cogley, Bridget. (June 12, 2018). "Rogers Stirk Harbour + Partners officially completes Three World Trade Center in New York City".
- Kim, Betsy. (June 12, 2018). "3 World Trade Center Opens to the Public".
- Dunlap, David W.. (March 18, 2015). "Considering a Counterintuitive Path to Escape a Fire: The Elevator". The New York Times.
- (February 20, 2020). "Massive James Rosenquist Mural Unveiled in Lobby of 3 World Trade Center the Financial District".
- Gannon, Devin. (February 27, 2025). "A fish sculpture by Frank Gehry now hangs in the lobby of 3 World Trade Center".
- Rahmanan, Anna. (March 1, 2025). "This giant copper sculpture of a fish by Frank Gehry is now on display at the World Trade Center".
- (June 13, 2018). "3 World Trade Center".
- Morris, Keiko. (September 11, 2015). "At World Trade Center Towers, Outside Is In". Wall Street Journal.
- Gardner, James. (June 1, 2018). "Beware: World Trade Weariness".
This article was imported from Wikipedia and is available under the Creative Commons Attribution-ShareAlike 4.0 License. Content has been adapted to SurfDoc format. Original contributors can be found on the article history page.
Ask Mako anything about 3 World Trade Center — get instant answers, deeper analysis, and related topics.
Research with MakoFree with your Surf account
Create a free account to save articles, ask Mako questions, and organize your research.
Sign up freeThis content may have been generated or modified by AI. CloudSurf Software LLC is not responsible for the accuracy, completeness, or reliability of AI-generated content. Always verify important information from primary sources.
Report